If Providers amend the Estimated Gateway Date, then the Expected Completion Date will also update in line, based upon the Max Assessment Duration.
Test Example | |
Expected Start Date | 23/03/2022 |
Expected Date Ready for EPA | 24/03/2023 |
Original Expected Completion Date | 25/03/2023 |
Max Assessment Duration | 30 days |
Estimated Gateway Date | Amended from 23/03/2022 → 24/04/23 |
New Expected Completion Date | 24/05/23 |
Once an apprentice has been confirmed for gateway, the standard and estimated gateway (expected ready for EPA) date become locked - the gateway must be unconfirmed before changes can be made.
...